Making for interesting progress at the moment.

Retaining footings are in, followed by the block retaining walls. Now giving some shape to the ground level. The site surroundings are considerably muddy, and the Brisbane City Council has definitely made a mess attempting to complete the sewer extension to the rear of the two adjoining properties. Hopefully they can complete their works in the next week or two.

The next step is to prepare for the concrete slab to the lower level. I intend to have this in place prior to our Xmas break.



Cheap labour - Charlie and Jarrod...

Retaining Walls in...


Macca - the footing pour.
Catch ya soon....
Mitch


Wednesday, November 5, 2008

New Position.....

Apologies for the delay in updating you all. Progress has been slow, so not much to report on....
The house is back down in its new position. Fixed on to the steel columns concreted into the ground. The process went smoothly and importantly with out any difficulties...
I am currently just chipping away at the minor internal alterations that need to take place for the new bathroom to be completed, along with attempting to reconnect all the services.
Enjoy the snaps and will be in touch....